-Christoph: simulation of the power deposition around the facility
(including inside the experimental hall and just outside of it) with
neutron fluence and dose
-Andrea: optimization of the horn+target with no reflector
Strasbourg group: reference drawings of the horn with strip lines (and
drawings of the facility ?)
-Piotr: first conceptual drawings of the mechanical structure supporting
the four horns, including services (Piotr please confirm this task)
-Chris: assess feasibility of the beryllium target/horn, obtain from T2K
informations and parameters of the target station, the decay tunnel and
the beam dump (including shielding thicknesses)
-Benjamin: FE model of the horn
-Marco: start preparing a note for the milestone "preliminary design of
target and collection" due in september