- Moss (Fred, Xiaochao):
- Chips fabrication started and the return is estimated by the end of april.
- Discussion started related to next submission focus on the development on ITS3 => MOSS-Like architecture with significant change in the read-out of the pixel array and with a constraint for the data bandwidth (which is not the case of the MOSS architecture).
- Some small dedicated chips could be added (not clear yet) and most probably related to ITS3.
- In summary, the next submission is a kind of "pre-production" --> planned to the end of 2023.
- Contribution of the IPHC to the next submission : mainly the read-out of the pixel array of the digital part and also power verification of the chip.
- Most (Szymon):
- Documentation almost finished.
- More news to come on the wednesday meeting and more is to come from NIKHEF.
- Most read-out will not be part of the ER2 submission. May be revisited after the ITS3.
- Most is of interest but not for ITS3.
- CE-65 (Andrei):
- Preparing the measurement: PCB and carrier board.
- Also analysis to complete the whole picture.
- Preparing some tests to other groups that are interested in measurement.
- Actually, leakage current measurement are in progress (with Kimmo).
- What are the questions that are still open.
- Szymon help Andrei with Analysis for the lab measurement and apply the pixel selection from the read-out.
- Many chips still need to be characterized (Human power and time for systematic measurements) ==> need to have more precision on required time and FTE to achieve these systematic measurements.T
- First estimation is about two weeks to finish the measurements.
- Analysis (Ziad):
- Found a missing parameter in the configuration file that induced error in the analysis: now fixed.
- Analysis no is (I hope) a matter of time.
Il y a un compte-rendu associé à cet événement.
Les afficher.