Presents: Nikita, Cyrille, David, Francesco, Paul, Yann, Yahya, Reina, Stephanie, Pascal, Thiziri
Bare modules:
- 1 BM IV done, 8 IV to go
- 9 BM metrology
Flex:
- 19 flex
- VI inspection photos done, but not in the localdb for all
- Metrology done, mass done
- 2x to be cleaned
- 4 flex Tecnomec naked, 1x Tecnomec
Gluing:
- 2x modules per day for the week = 6 modules
- Next week 3 modules
Metrology:
- Next-day metrology for each of the modules
Wirebonding:
- Starting wed, it is again unstable and we have no prediction now
Testing:
- PPP09, PPP16, PPP38 vers FINAL TESTS
- PPP34 at FINAL TESTS too, but with dead borders. To be investigated.
- One module broken (one resistor gone) probably to be repaired
- 3x modules to be tested post_parylene
- PPP62 electrical tests done, digital to be done
- PPP61 done
- PPP49(?) ... 2/4 FE working
- PPP48(?) dead
- PPP15 blocked in the localdb