Participants: Marc, Pascal, Marco, Thibaud, Yann, David, Giovanni C, Francesco
General news:
- ITk Week next week. Expected new discussion about the schedule
- New preproduction schedule: 50% before mid-Nov and the other 50% before end-Jan
- Wirebond protection is critical
- ITkPixV2 good tests except DM
- 100 wafers arrived yesterday
Wirebonding
- Axial light camera still not working! Maintenance needed
- Pull-test still not top, but parameters still possible to optimise (7.5 mean, few with very low value under 5). Always on the pad side
- Compressed air reference
- IRFU discussion for WB
- Genova bonded 3 SCC ITkPixV1.1 modules and we need to wirebond the last 3 SCC here
- Target is IRRAD before mid-Oct
Assembly
Testing
- LV is OK for 8 modules
- HV board is there but cables are missing. We have 1 full cable maybe a second
- Monitoring board is done, we should receive the PCB soon
- We should re arrange the room with ergonomics in mind
- We received the materials to build the 8-modules support
-
Xray
- Lead to be covered with vinyl
- Earth plug to be produced / installed
Il y a un compte-rendu associé à cet événement.
Les afficher.