Presents: Marco B, Pascal, David, Eric, Yann, Francesco C, Philippe
General news:
- We are supposed to assemble 6 modules FastQC for irradiation at CYRIC in June, but we don't have flex yet. Not obvious to be able to do everything in time.
- We should create a common pool for orders to RS, Farnell, etc to optimize them
Wirebonding
- v3.2 program to be finalized, possible on the dummy
- 2/4 FE working on the first digital bonded
- 4/4 FE OK on the second digital. No issues during WB
- Maybe on wed another module will be done
- Pascal will go in vacation and be back on the 8th of may
Gluing
- MArco/Francesco 1st test, Thibaud/Paul 2nd test. Glue weight ok, Wrong calib procedure, too much height, bad coverage after curing. See slides
Testing
- 4-out cable done. The second 4-outs cable is under production
- Cable tested is OK. Ch4 of the CAEN card has wrong voltage in output
- To be tested on a real quad module
- Need to finish the distribution card, maybe on thursday
- Support material re-ordered from a new supplier, waiting for the material (6-10 jj)
X-Ray
- Cabinet to be installed this week
- Support for the fan arrived but we'll leave the current in place unless there are issues
Il y a un compte-rendu associé à cet événement.
Les afficher.