Meeting ITk LPNHE
Join Zoom Meeting
https://cern.zoom.us/j/94940524377?pwd=dnI4NnZUWGNMN1ZpRFJncFU1ZlMrQT09
Presents: Yann, Marc, Lydia, Giovanni, Brigitte, Bianca&Tom, Marco, Artur
General:
- FDR today, tomorrow and next week. Mechanical protection detached from main review.
Wirebonding:
- status of the clean room: mid-june was optimistic, no real date. We could discuss moving under the plafond soufflant
- order of cards: done for Lightweight, no news for 2nd lot of RD53A.
- status of the wirebonding machine orders: wire ordered, some progress about the outil
- We should review the proposed V3.0 of the flex
Assembly:
- pump mainteinance / installation: Yann will plan with Michael. This week. Ask if possible to install on the little room on the side in order to avoid the noise
Testing:
- support for testing in the climate chamber: under fabrication this week
- data merging tests progress: report last wed, new report tomorrow, new quad tomorrow
- Box to transport SCC ordered yet, maybe we can build it @ lab.
X-Ray:
- devis received, reasonable price, we'll start all the orders. 8 weeks of fabrcation time