Meeting ITk LPNHE
Join Zoom Meeting
https://cern.zoom.us/j/94940524377?pwd=dnI4NnZUWGNMN1ZpRFJncFU1ZlMrQT09
Presents: Yann, Brigitte, Luc, Bianca, Pascal, Mykola, Lydia
General news: ITkPix digital activity is ramping up, assembly done in IRFU-IJCLab. We are ahead in the testing.
Wirebonding:
- new constraints on ITKPix wirebonding: same-pad wires can't touch. We must understand if this constraint is real or useful.
- differences between schematic and bonding map to understand
- we must ask for dummies
- parylene masking of SCC is very difficult, one module destroyed (2050). We must build a rigid cover like Liverpool https://indico.cern.ch/event/944362/contributions/3968293/attachments/2085111/3502832/jtaylor_HVp_WG_050820.pdf
Assembly:
- MMT yet to be tested after moving under the plafond soufflant
- Vacuum to be installed. Maybe in the next room? (reserve com)
Testing:
- Structure to test modules in the climate chamber under assembly, maybe done next week
- Priority on testing the data merging with the digital ITkPix V1.0
X-ray:
- The company has not worked on a quote, they will work on it now and give a quote by the end of the week