Presents: Yann, Yahya, Paul, Thiziri, David, Francesco, Cyrille, Thibaud, Oleksandra, Pascal, Stephanie, Julien
General news:
- We are asked a plan for SQ
Probe station:
- Agilent do not work, let's home
- Possibility: do the IVs in IJCLab
Metrology:
- We received 1 Digital 2 Bare Modules 2 Flex
- 2 Flex metrology done
- 1 Digital "metrology" done
- Post-gluing metrology on Leonardo done. One FE is near to detach
- Post-gluing digital metrology ongoing
Gluing:
- 1 Digital V2 glued
- Last Leonardo module glued
- We need to write to Goettingen about the screw height
- Ask for new stencil
Wirebonding:
- Meeting with Pascal, Stephanie, Cyrille, Nabil about CUBIC:
- Two weeks starting from next for CUBIC then it is done
- PPP49 done
- We will start with the digital V2 this afternoon
- Keep track of the transducer screws: we are expecting a shipping, to be asked to MB
- Torque driver for ultrasonic transducer is OK now
- Base plate for wirebonding to be flatten and alignment pins is too high
Testing:
- PPPV2_5 and PPPV2_6 inital tests done
- Cold is problematic for 05
- Issues with RS for the interlock of the CC door
Outer barrel wirebond protection:
- Thiziri is back from CERN with the tool tested @ CERN. Vacuum was good.
- New tests today
Xray:
- A study of how much hits we can collect before crashing has been done
- Scripts to do incremental masking developed
- Another script for plotting has been done
- It worked for V2!
Various:
- Video of operations should be uploaded somewhere box.in2p3.fr
-