- Test of CE65, Sergey
- inventory => 4 more carriers needed to be populated with flavors A,B,C,D
- review of modifications under way (on-going discussion with Andrei, Kimmo) => decision in one week
- Standard cell design, Fred
- still in preparation to get the list of cells to be designed and checked by CERN
then cells will be distributed to various institutes
=> work sharing still under discussion - For MOSS:
- concern about ESD protection for pads, possibly interfering with back-bias, under discussion
- addition of capacitive filler for row steering bloc finished by XiaoChao
- still in preparation to get the list of cells to be designed and checked by CERN
- CE-65v2 design, Christine reporting for Andrei
- version C (charged collection):
- pixel with 18um finished, with AC version (best ENC perf in CE-65v1)
- will be adapted to 22.5 um and hexagonal versions
- for 15 um pitch, a new design will be needed (remove some bias lines for instance...)
will difficult to match submission by end-of-April
=> reproduce CE-65v1 but adapt whatever changes (pad ring, metals ...)
!!!! need to choose which flavour (A, B or C) - we drop the true hexagonal design
- version A (FE studies)
- will be copied from the 18 um pixel version C
- NEED as starting point the FE optimised by CERN (true for option D as well)
- version D
- restrict to 18 and 18hexsq versions
- Szymon fears that 22.5 will be not so efficient ?
- if time allow, we add 15um
- version C (charged collection):
- MOST design, Szymon
- isolation between power domain under questions
- work for Szymon: still on-going
- Visit of IP2I colleagues
- possibly April 7th & 8th
==> Next meeting Wednesday April 6th