Meeting ITk LPNHE

Europe/Paris
Description

Join Zoom Meeting
https://cern.zoom.us/j/94940524377?pwd=dnI4NnZUWGNMN1ZpRFJncFU1ZlMrQT09

 

Presents: Giovanni C, Marco B, Yann, Pascal, Brigitte, Marc, Francesco, Bertand, Artur

Wirebonding

* GO modules completed. Good pull-up tests. Gluing issues on the sides of the flex

* Paris8 (171) bad flex quality. We'll do some tests to understand the pull force, in the meanwhile we wait for other modules. Only if there will be no other quad to do we'll start to bond this

SCC

* Received two quotes

* We ask to split the quotes in a small (15) and lager (35) runs

* Box: no response for an industrial production, we'll print 5-10 and then ask again

Support climate chamber

* Yann will look at the heatsink and find a component to buy

Support for testbeam

* In the printing queue

Camera for VI

* Support is going to be printed next week

* Long cable for Raspberry Camera

Testing QC

* All hardware capabilities are there

* We need to standardize all steps to aim for a quick qualification