• E-EB tomorrow
  • Milestones and deliverables:
    • M2.2 (M18 -> August): Progress report. Initial datalake pilot with at least 3 sites.
      • Task leaders please send input with a summary status of your activities before end of July
      • All partners: report on hiring status and FTE commitment in WP2 before end of July
    • M2.3 (M22 -> November): Second WP2 workshop to analyse performance of the datalake pilot
      • Means of verification:Workshop summary report.
      • Workshop organisation. We have two volunteering sites. Propose to start preparations and plan for a face to face workshop with virtual capabilities. 
        • Caveats:
          • Prepare for good percentage of people attending remotely
          • Things can change rapidly. Fallback of a virtual workshop ready until last minute.
  • Organisation and meetings during summer period :
    • 15th July:
      • T2.2 Advancements on QoS experiments input and QoS further deployment plans  (Paul)
      • T2.5 Update (Andrea)
    • 29th July: T2.3 and T2.4 updates (Rosie kindly agreed to chair the meeting, thanks!)
    • 12th August: cancelled
    • 26th August: T2.1 Datalake status and plans for the performance analysis
  • Prepare a short communication note for WP6 before August with the different data and activities we have at the moment in the datalake.